Perfoplaque(plasterboard) Installation |
|
|
|
|
Plates are either nailed of fixed on Still-Prim® supports |
|
|
|
|
The mat is screwed on the plaster board |
Some place is left for future partition walls |
|
|
|
|
The distribution piping is set up approx. 2 cm (0.8 in) above the perforated board |
|
|
|
The mat can be held during its mounting |
|
|
|
|
|
Details of the piping |
|
|
|
|
Distribution piping |
|
|
|
|
Dilation joints have to be considered, as well as dissociating the wall from the ceiling |
|
|
|
|
Plaster projection |
Traditional plaster painting |
| More detailed information is available for installation of perfoplaque ceilings (pdf format, in French) |
|